Wednesday, 17 April 2013 10:49

AQUA Notice: Summer 2013 Construction on Route 390

March 26, 2013

Dear Aqua Mountainhome Customers:

I am writing to let you know about a water infrastructure improvement project that Aqua Pennsylvania, Inc. (Aqua) is scheduled to begin in your area in the next week.

Aqua will begin an $840,000 project to replace approximately 4,858 feet of old undersized pipe with new 8-inch ductile iron pipe that will eliminate leaks and improve service reliability for customers. The project on Rt. 390 will extend from Price's Drive south to the area near CVS.

Construction is scheduled to take place Monday through Friday between 7:30 a.m. and 3:30 p.m. and is expected to be complete late this summer.

Throughout the construction there might be temporary inconveniences including interruptions to traffic, periods of cloudy or discolored water, low water pressure, or no water. We will do our best to minimize these inconveniences and ask for your patience during construction.

Disturbed surfaces will be fully restored upon completion of the project. Aqua will have an inspector on site to ensure a quality project and to address any concerns you might have.

We appreciate your patience during this temporary inconvenience as we work to make a permanent improvement in your community. Sincerely, ~~ Manager, Honesdale Division

Aqua Pennsylvania, Inc. 1775 N. Main Street Honesdale, PA 18431 T: 570.647.0358 F: 570.647.0580 www.aquaamerica.com